Which of the following is NOT a characteristic of tasks on the critical path? 

A. They have the least amount of slack. 

B. They have no room for delay without impacting the project's completion time. 

C. They are not dependent on any other tasks in the project. 

D. Their total duration contributes directly to the project's duration.

Avatar
Discard
Best Answer

C. They are not dependent on any other tasks in the project.