Which formula is used to calculate the expected time for a task in PERT?

A. (O+4M+P)/6(O + 4M + P)/6(O+4M+P)/6

B. (O+M+P)/3(O + M + P)/3(O+M+P)/3

C. (M+P)/2(M + P)/2(M+P)/2

D. (O+M+2P)/4(O + M + 2P)/4(O+M+2P)/4