Welcome!

This community is for professionals and enthusiasts of our products and services.
Share and discuss the best content and new marketing ideas, build your professional profile and become a better marketer together.

This question has been flagged
4 Replies
46 Views

PERT activity time is calculated using the formula (Optimistic Time + 4 * Most Likely Time + Pessimistic Time) / 6 is Expected Time.

Avatar
Discard
Best Answer

true

Avatar
Discard
Best Answer

T

Avatar
Discard
Author Best Answer

?

Avatar
Discard
Best Answer

Answer: True


Avatar
Discard